Issues white paper 2026
BIM Clash Report 2026
Which clashes HOOK’s BIM coordination finds most, how they happen, why, and how they get fixed. Based on 1,087 tagged issues from 1 projects.
Live figures from HOOK’s issue log, updated 10 Nov 2026, 01:53 (Bangkok time).
The most common clash behavior was Hard Clash: one in every 3 clashes we tagged.
- Structure × MEP
- Architecture × MEP
- Structure × Architecture
- MEP × MEP
- Structure
- Architecture
- Discipline not recorded
Hover or tap a floor to see its clashes. Click a dot to see that clash up close. Drag to turn, right-drag or two fingers to move, scroll or pinch to zoom.
Ground floor & mezzanine
514 issues- Architecture × MEP129
- MEP × MEP122
- Structure × MEP113
- Structure × Architecture78
- Architecture41
- Structure30
- Discipline not recorded1
- Ceiling × Pipe · 49
- Beam × Pipe · 35
- Ceiling × Terminal (Diffuser, Sprinkler, Lighting) · 30
1 issues had no floor recorded and are not drawn.
Each dot stands for about 50 clashes from HOOK’s issue log, drawn on the floor they were recorded on, where the two elements involved meet, and coloured by the disciplines involved. The building is illustrative.
- 1,087
issues reviewed
1,087 tagged by type, cause and fix
- 1
projects
Residence
- 34.5%
most common clash behavior: Hard Clash
- 67.1%
most common root cause: Lack of Coordination
Shares on this page are of the 1,087 tagged issues.
What collides
The element pairs that clash most
Beam × Pipe topped the list with 92 clashes, 8.5% of all tagged issues.
Pick a pair to see it in 3D, then switch between the clash and the fix.
- Beam
- Pipe
- Clash zone
- After the fix
How Beam × Pipe clashes
- 01Hard Clash71.7%Two solid elements take up the same space, such as a pipe running through a beam.66 issues
- 02Penetration26.1%A service passes through a wall, slab or beam where no opening was planned.24 issues
- 03Location Conflict9.8%An element is placed where another discipline needs the space.9 issues
Share of this pair’s 92 clashes. One clash can carry more than one behavior.
How Ceiling × Pipe clashes
- 01Exposed49.3%An element that should be hidden shows below a ceiling or outside a finish.33 issues
- 02Wrong Elevation40.3%An element sits at the wrong height for the levels and elements around it.27 issues
- 03Hard Clash34.3%Two solid elements take up the same space, such as a pipe running through a beam.23 issues
Share of this pair’s 67 clashes. One clash can carry more than one behavior.
How Ceiling × Terminal (Diffuser, Sprinkler, Lighting) clashes
- 01Hard Clash33.3%Two solid elements take up the same space, such as a pipe running through a beam.20 issues
- 02Misalignment31.7%Elements that should line up across disciplines are offset from each other.19 issues
- 03Wrong Elevation21.7%An element sits at the wrong height for the levels and elements around it.13 issues
Share of this pair’s 60 clashes. One clash can carry more than one behavior.
How Pipe × Shear Wall clashes
- 01Penetration77.3%A service passes through a wall, slab or beam where no opening was planned.34 issues
- 02Missing Opening68.2%A service needs an opening, sleeve or shaft that is not in the model.30 issues
- 03Hard Clash20.5%Two solid elements take up the same space, such as a pipe running through a beam.9 issues
Share of this pair’s 44 clashes. One clash can carry more than one behavior.
How Ceiling × Duct clashes
- 01Hard Clash40.5%Two solid elements take up the same space, such as a pipe running through a beam.15 issues
- 02Exposed37.8%An element that should be hidden shows below a ceiling or outside a finish.14 issues
- 03Wrong Elevation37.8%An element sits at the wrong height for the levels and elements around it.14 issues
Share of this pair’s 37 clashes. One clash can carry more than one behavior.
How Beam × Slab clashes
- 01Misalignment35.3%Elements that should line up across disciplines are offset from each other.12 issues
- 02Hard Clash32.4%Two solid elements take up the same space, such as a pipe running through a beam.11 issues
- 03Wrong Elevation29.4%An element sits at the wrong height for the levels and elements around it.10 issues
Share of this pair’s 34 clashes. One clash can carry more than one behavior.
How they collide
Clash behaviors
Hard Clash led the behaviors at 34.5%. A behavior describes what two elements do to each other, such as a pipe running through a beam.
Behavior
- 01Hard Clash34.5%Two solid elements take up the same space, such as a pipe running through a beam.375 issues
- 02Misalignment17.4%Elements that should line up across disciplines are offset from each other.189 issues
- 03Wrong Elevation17.1%An element sits at the wrong height for the levels and elements around it.186 issues
- 04Exposed14.9%An element that should be hidden shows below a ceiling or outside a finish.162 issues
- 05Location Conflict11.1%An element is placed where another discipline needs the space.121 issues
- 06Penetration7.6%A service passes through a wall, slab or beam where no opening was planned.83 issues
- 07Clearance Violation6.7%The gap needed for access, maintenance or insulation is missing.73 issues
- 08Size Conflict5.6%An element is too big for the space or opening it has to fit into.61 issues
Elements found in clashes
How often each element shows up in a tagged clash, on either side.
- 01Pipe32.8%357 issues
- 02Beam22.2%241 issues
- 03Ceiling19.8%215 issues
- 04Slab17.8%193 issues
- 05Terminal (Diffuser, Sprinkler, Lighting)14.1%153 issues
- 06Equipment12.7%138 issues
- 07Wall11.4%124 issues
- 08Duct10%109 issues
Why
Root causes
The root cause is why a clash reached the model in the first place. It shows which step of the process needs to change.
of the clashes we tagged traced back to Lack of Coordination.
Root cause
- 01Lack of Coordination67.1%Disciplines modelled the same zone without agreeing who goes where.729 issues
- 02Incorrect LOD11.6%An element was modelled at too low a level of detail to check properly.126 issues
- 03Model Not Linked / Outdated8.5%A team worked against a missing or old copy of another discipline’s model.92 issues
- 04Design Change Not Updated7.2%The design changed, but the model did not follow.78 issues
- 05Late Design Input3.3%Design information arrived after the model in that area was built.36 issues
- 06Assumption Conflict0.7%Two teams filled the same gap in the design with different assumptions.8 issues
How we fix them
Solutions
The most common fix was MEP to reroute, used on 25.9% of tagged issues.
Solution type
- 01MEP to reroute25.9%282 issues
- 02BIM to coordinate & recheck22.9%249 issues
- 03Change Elevation21.3%231 issues
- 04Shift Element20.6%224 issues
- 05AR to revise model12.9%140 issues
- 06ST to confirm structure11.1%121 issues
- 07Reroute (Duct / Pipe / Tray)9.9%108 issues
- 08Refer to Consultant7.2%78 issues
From cause to fix
The root cause and solution pairs that came up most often.
- 01Lack of Coordination fixed by MEP to reroute22.2%241 issues
- 02Lack of Coordination fixed by Shift Element16.6%180 issues
- 03Lack of Coordination fixed by Change Elevation14.1%153 issues
- 04Lack of Coordination fixed by Reroute (Duct / Pipe / Tray)8.9%97 issues
- 05Lack of Coordination fixed by ST to confirm structure7.6%83 issues
- 06Incorrect LOD fixed by BIM to coordinate & recheck7.3%79 issues
- 07Lack of Coordination fixed by AR to revise model7.3%79 issues
- 08Lack of Coordination fixed by BIM to coordinate & recheck6.8%74 issues
Disciplines involved
Structure appeared in more tagged clashes than any other discipline.
Discipline tags
- 01Structure51.2%557 issues
- 02Sanitary37.2%404 issues
- 03Architecture32.8%357 issues
- 04Interior25.2%274 issues
- 05Mechanical24.6%267 issues
- 06Electrical15.5%169 issues
- 07Landscape7.4%80 issues
- 08Fire Protection2%22 issues
Discipline flags on all 1,087 issues
Set on every issue in the log, tagged or not, so these counts use the larger sample.
- Mechanical (ME)
- 754
- Structure (ST)
- 563
- Architecture (AR)
- 351
- Interior (ID)
- 215
- Landscape (LA)
- 42
- Facade (FC)
- 21
How this report was made
- Source
HOOK’s BIM coordination issue log (hook-tracker)
- Issues logged
23 October 2026 to 23 October 2026
- Data as of
10 Nov 2026, 01:53
- Projects
1 (Residence)
- Sample size
1,087 issues logged, 1,087 of them tagged (100%)
- Status at cutoff
Closed 924 · Open 163
- Priority
Minor 686 · Major 400 · Regulation 1
Every share on this page is a share of tagged issues. The coordination team adds the tags by hand, so coverage varies from project to project.
One issue can carry several tags, for example two elements and two behaviors, so the shares in a list can add up to more than 100%.
Project names, drawings and issue descriptions stay private. Only counts are published, grouped by project type.
The figures on this page come straight from the coordination issue log and refresh about every 10 minutes. Each year’s edition is kept as an archive with its figures fixed.